Skid-mounted vs site-built blending plants: which suits your project?

Skid-mounted and site-built chemical blending plants compared on size, site work, schedule, shipping, expansion and cost, and when to combine the two.

A chemical blending plant can be built in two ways. A site-built plant is erected at site: tanks set on foundations or a structure, then piped, wired and commissioned there. A skid-mounted plant is built in modules in the fabricator's works, each module carrying its tanks, agitators, pumps, piping and instruments on a steel frame, then shipped and connected at site. Most plants that are not very large end up as a mix of the two. This guide sets out how to decide.

What a skid-mounted plant is

A skid is a self-contained section of the plant on a base frame: for example a blend tank with its agitator, load cells, pump and filter, or a dosing module with additive tanks and metering pumps, or a filling module. The piping and wiring inside the skid are completed in the works, and the skid is run and tested before dispatch. At site, the work is setting the skid down, connecting the lines between skids and to the tank farm, and connecting power and controls.

Where skids win

  • Less work at site. Most fabrication, piping and testing happen in the works, where quality is easier to control. This matters most at remote sites, in hot climates and where skilled site labour is scarce or expensive.
  • Shorter site schedule. Skids can be built while the civil work is done at site, so the two run in parallel instead of one after the other.
  • Testing before shipment. Agitators, pumps and controls are run in the works, so faults are found before the plant is on site.
  • Expansion and relocation. A further blend skid can be added later, and a skid can be moved if the plant is relocated.

Where site-built wins

  • Large tanks. Tanks too large to ship as one piece, such as big storage tanks in the tank farm, are built or set at site in any case.
  • Large, integrated plants. When many tanks share a structure and platforms, building the structure at site can be simpler than splitting it into transportable modules.
  • Layout freedom. A site-built plant fits an existing building or plot more easily than modules sized for transport.

Shipping limits shape the skids

A skid has to travel by road and, for export, in a container or on a flat rack. Container dimensions and road limits set the maximum skid size, and with it the largest blend tank that can go on one skid. We plan skid sizes and lifting points with the route in mind from the start, so that nothing has to be cut or re-welded at site.

The usual answer: both

In most oilfield and specialty chemical plants, the tank farm and large storage are site-built, while the blend tanks, dosing, additive systems and filling are supplied as skids. This puts the complex, closely tested equipment in the works and leaves the simple, bulky equipment to site.

Questions to settle early

  • How far is the site, and how is it reached: road, sea, container or break-bulk?
  • What size are the largest blend tanks, and do they fit on a transportable skid?
  • Is site labour available and affordable for piping and electrical work?
  • Is the plant likely to be expanded or moved?
  • Is the plant inside a hazardous area, and does that affect which equipment can be pre-assembled together?

We engineer oilfield chemical blending plants and chemical blending plants both ways, and often as a mix. Send the product list, output and site location and we will propose the split.